Reason:
1. In terms of personnel: the division of labor is unclear after an abnormal shutdown occurs.
2. Glue: After an abnormal shutdown, no one pays attention to the time, and the glue solidifies in advance.
3. After abnormal shutdown, there is no marking and notification to palletizing for bonding confirmation.
Solution:
1. Everyone's responsibilities are clarified, and what to do after abnormal shutdown occurs.
2. After abnormal shutdown, pay attention to the countdown time, and the machine must be turned on when the time is up.
3. If the treatment is not completed after the countdown sounds, mark it after turning on the machine, and remove the cleanroom panel to check the bonding after the track is out